Bank Stabalisation & New Tow Path

Project: Bank Stabalisation & New Tow Pat
Client: CYC
Value: £110,000

Phase 2 of works (Phase 1 was similar works completed in 2014)

 

Rake out and repoint all 45 degree esplanade retaining wall.

 

Break out and remove the concrete tow path

Re-concrete new tow-path.

 

Bank stabilisation major works.

 

The only access available to carry out these works safely is via a work boat.

 

Dealing with the general public and all river users.

 

Protection of existing structures.

 

Working alongside divers employed by CYC to help secure the existing river bank construction.